C-127/02 (reference for a preliminary ruling) - Waddenvereniging and Vogelbeschermingsver eniging

AuthorEuropean Commission
Pages95-100

Page 95

Judgment of the Court (Grand Chamber) of 7 September 2004. - Landelijke Vereniging tot Behoud van de Waddenzee and Nederlandse Vereniging tot Bescherming van Vogels v Staatssecretaris van Landbouw, Natuurbeheer en Visserij. - Reference for a preliminary ruling: Raad van State - Netherlands. - Directive 92/43/EEC -Conservation of natural habitats and of wild flora and fauna - Concept of "plan' or "project' - Assessment of the implications of certain plans or projects for the protected site. http://europa.eu.int/eur-lex/lex/LexUriServ/LexUriServ.do?uri=CELEX:62002J0127:EN:HTML

The reference for a preliminary ruling concerns the interpretation of Article 6 of the Habitats Directive was made in proceedings between the National association for conservation of the Waddenzee ('the Waddenvereniging') and the Netherlands association for the protection of birds ('the Vogelbeschermingsvereniging') on the one hand and the Secretary of State for agriculture, nature conservation and fisheries ('the Secretary of State') on the other in respect of licences which the latter issued to the Cooperative producers' association of Netherlands cockle fisheries ('the PO Kokkelvisserij') for the mechanical fishing of cockles in the special protection area (SPA) of the Waddenzee, classified within the meaning of Article 4 of the Birds Directive.

By decisions of 1 July 1999 and 7 July 2000 (the decisions at issue in the main action'), the Secretary of State issued licences to PO Kokkelvisserij, subject to certain conditions, to engage in mechanical cockle fishing in the Waddenzee SPA during the periods from 16 August to 25 November 1999 and 14 August to 30 November 2000 respectively. The Waddenvereniging and the Vogelbeschermingsvereniging challenged those decisions before the Secretary of State, who, by decisions of 23 December 1999 and 19 February 2001, held that the complaints made against the decisions at issue in the main action were not founded and rejected the applications against them. Those nature protection associations brought an action against those rejections before the Council of State. They claimed in essence that cockle fishing, as authorised by the decisions at issue in the main action, causes permanent damage to the geomorphology, flora and fauna of the Waddenzee's seabed. They also submitted that such fishing reduces the food stocks of birds which feed on shellfish, causing a decline in their populations, in particular for oystercatchers and eider ducks. The Waddenvereniging and the Vogelbeschermingsvereniging also claimed that those decisions were contrary to the Habitats and Birds Directives. As regards the correct transposition of Article 6(2) to 6(4) of the Habitats Directive into Netherlands law, the Council of State states that Article 12 of the Natuurbeschermingswet, although not expressly intended to implement the obligations laid down in Article 6(2) of the Habitats Directive, may be interpreted in a manner consistent with that provision. Similarly, the Natuurbeschermingswet does not contain rules which implement Article 6(3) and (4) of that Directive. Nor are there generally binding rules intended to implement the provisions of those two paragraphs which are otherwise applicable to the Waddenzee. The national court also states that according to the Waddenvereniging and the Vogelbeschermingsvereniging, in view of the expansion of cockle fishing in the Waddenzee SPA, there is a plan or project' which should be subject to appropriate assessment' in accordance with Article 6(3) of the Habitats Directive whereas the Secretary of State contends that the activity in question, inasmuch as it has been carried on for many years without any intensification, falls within Article 6(2) of that Directive. As regards the relationship between Article 6(2) and 6(3) of the Habitats Directive, the Waddenvereniging and the Vogelbeschermingsvereniging submit that although the activity for which licences were granted must be described as a plan' or project' within the meaning of Article 6(3), it must nevertheless be examined in the light of Article 6(2). It is therefore appropriate to consider whether Article 6(3) must bePage 96 regarded as a specific application of the rules in Article 6(2), so that those two paragraphs must be applied cumulatively, or as a provision with a separate, independent purpose, so that Article 6(2) relates to existing use while Article 6(3) applies to new plans or projects. The Council of State asks under what conditions an appropriate assessment' of the effect of the plan or project on the site concerned must be carried out. In addition, it asks what the criteria are on the basis of which it must be determined whether appropriate steps' or an appropriate assessment' are concerned, also in the light of the requirement laid down in Article 6(3) of the Habitats Directive for the competent authorities to agree to a plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned. Finally, the national court considers it relevant to know whether Article 6(2) and (3) of the Habitats Directive has direct effect. In those circumstances, the Council of State decided to stay the proceedings and to refer the following questions to the Court of Justice for a preliminary ruling:

  1. (a) Are the words plan or project in Article 6(3) of the Habitats Directive to be interpreted as also covering an activity which has already been carried on for many years but for which an authorisation is in principle granted each year for a limited period, with a fresh assessment being carried out on each occasion as to whether, and if so in which sections of the area, the activity may be carried on?

    (b) If the answer to Question 1(a) is in the negative, must the relevant activity be regarded as a plan or project if the intensity of this activity has increased over the years or an increase in it is made possible by the authorisations?

  2. (a) If it follows from the answer to Question 1 that there is a plan or project within the meaning of Article 6(3) of the Habitats Directive, is Article 6(3) of the Habitats Directive to be regarded as a special application of the rules in Article 6(2) or as a provision with a separate, independent purpose in the sense that, for example:

    (i) Article 6(2) relates to existing use and Article 6(3) to new plans or projects, or

    (ii) Article 6(2) relates to management measures and Article 6(3) to other decisions, or

    (iii) Article 6(3) relates to plans or projects and Article 6(2) to other activities?

    (b) If Article 6(3) of the Habitats Directive is to be regarded as a special application of the rules in Article 6(2), can the two subparagraphs be applicable cumulatively?

  3. (a) Is Article 6(3) of the Habitats Directive to be interpreted as meaning that there is a plan or project once a particular activity is likely to have an effect on the site concerned (and an appropriate assessment must then be carried out to ascertain whether or not the effect is significant) or does this provision mean that an appropriate assessment has to be carried out only where there is a (sufficient) likelihood that a plan or project will have a significant effect?

    (b) On the basis of which criteria must it be determined whether or not a plan or project within the meaning of Article 6(3) of the Habitats Directive not directly connected with or necessary to the management of the site is likely to have a significant effect thereon, either individually or in combination with other plans or projects?

  4. (a) When Article 6(3) of the Habitats Directive is applied, on the basis of which criteria must it be determined whether or not there are appropriate steps within the meaning of Article 6(2) or an appropriate assessment, within the meaning of Article 6(3), in connection with the certainty required before agreeing to a plan or project?

    (b) Do the terms appropriate steps or appropriate assessment have independent meaning or, in assessing these terms, is account also to be taken of Article 174(2) EC and in particular the precautionary principle referred to therein?

    (c) If account must be taken of the precautionary principle referred to in Article 174(2) EC, does that mean that a particular activity, such as the cockle fishing in question, can be authorised where there is no obvious doubt as to the absence of a possible significant effect or is that permissible only where there is no doubt as to the absence of such an effect or where the absence can be ascertained?

  5. Do Article 6(2) or Article 6(3) of the Habitats Directive have direct effect in the sense that individuals may rely on them in national courts and those courts must provide the protection afforded to individuals by the direct effect of Community law, as was held inter alia in Case C-312/93 Peterbroeck?'

First question

Question 1(a)

By Question 1(a), the national court in essence asks whether mechanical cockle fishing which has been carried on for many years but for which a licence is granted annually for a limited period, with each licence entailing aPage 97 new assessment both of the possibility of carrying on that activity and of the site where it may take place, falls within the concept of plan' or project' within the meaning of Article 6(3) of the Habitats Directive.

The 10th recital in the preamble to the Habitats Directive states that an appropriate assessment must be made of any plan or programme likely to have a significant effect on the conservation objectives of a site which has been designated or is designated in future'. That recital finds expression in Article 6(3), which provides inter alia that a plan or project likely to have a significant effect on the site concerned cannot be authorised without a prior assessment of its effects. The Habitats Directive does not define the terms plan' and project'. By contrast, Council Directive 85/337/EEC of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment, the sixth recital in the preamble to which states that development consent for projects which are likely to have significant effects on the environment should be granted only after prior assessment of the likely significant environmental effects of these projects has been carried out, defines project' as follows in Article 1(2):

- the execution of construction works or of other installations or schemes,

- other interventions in the natural surroundings and landscape including those involving the extraction of mineral resources.'

An activity such as mechanical cockle fishing is within the concept of project' as defined in the second indent of Article 1(2) of Directive 85/337. Such a definition of project' is relevant to defining the concept of plan or project as provided for in the Habitats Directive, which, as is clear from the foregoing, seeks, as does Directive 85/337, to prevent activities which are likely to damage the environment from being authorised without prior assessment of their impact on the environment. Therefore, an activity such as mechanical cockle fishing is covered by the concept of plan or project set out in Article 6(3) of the Habitats Directive. The fact that the activity has been carried on periodically for several years on the site concerned and that a licence has to be obtained for it every year, each new issuance of which requires an assessment both of the possibility of carrying on that activity and of the site where it may be carried on, does not in itself constitute an obstacle to considering it, at the time of each application, as a distinct plan or project within the meaning of the Habitats Directive.

The answer to Question 1(a) must therefore be that mechanical cockle fishing which has been carried on for many years but for which a licence is granted annually for a limited period, with each licence entailing a new assessment both of the possibility of carrying on that activity and of the site where it may be carried on, falls within the concept of plan' or project' within the meaning of Article 6(3) of the Habitats Directive.

Question 1(b)

In the light of the reply to Question 1(a), there is no need to reply to Question 1(b).

Second question

By its second question, the national court in essence asks what the relationship is between Article 6(2) and Article 6(3) of the Habitats Directive.

It should be recalled that Article 6(2) of the Habitats Directive, in conjunction with Article 7 thereof, requires Member States to take appropriate steps to avoid, in SPAs, the deterioration of habitats and significant disturbance of the species for which the areas have been designated. Article 6(3) of the Habitats Directive provides that the competent national authorities are to authorise a plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon only after having ascertained, by means of an appropriate assessment of the implications of that plan or project for the site, that it will not adversely affect the integrity of the site. That provision thus establishes a procedure intended to ensure, by means of a preliminary examination, that a plan or project which is not directly connected with or necessary to the management of the site concerned but likely to have a significant effect on it is authorised only to the extent that it will not adversely affect the integrity of that site. The fact that a plan or project has been authorised according to the procedure laid down in Article 6(3) of the Habitats Directive renders superfluous, as regards the action to be taken on the protected site under the plan or project, a concomitant application of the rule of general protection laid down in Article 6(2). Authorisation of a plan or project granted in accordance with Article 6(3) of the Habitats Directive necessarily assumes that it is considered not likely adversely to affect the integrity of the site concerned and, consequently, not likely to give rise to deterioration or significant disturbances within the meaning of Article 6(2). Nevertheless, it cannot be precluded that such a plan or project subsequently proves likely to give rise to such deterioration or disturbance, even where the competent national authorities cannot be held responsible for any error. Under those conditions, application of Article 6(2) of the Habitats Directive makes it possible to satisfy the essential objective of the preservation and protection of the quality of thePage 98 environment, including the conservation of natural habitats and of wild fauna and flora, as stated in the first recital in the preamble to that Directive.

The answer to the second question must therefore be that Article 6(3) of the Habitats Directive establishes a procedure intended to ensure, by means of a preliminary examination, that a plan or project which is not directly connected with or necessary to the management of the site concerned but likely to have a significant effect on it is authorised only to the extent that it will not adversely affect the integrity of that site, while Article 6(2) of the Habitats Directive establishes an obligation of general protection consisting in avoiding deterioration and disturbances which could have significant effects in the light of the Directive's objectives, and cannot be applicable concomitantly with Article 6(3).

Third question

Question 3(a)

According to the first sentence of Article 6(3) of the Habitats Directive, any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, is to be subject to appropriate assessment of its implications for the site in view of the site's conservation objectives. The requirement for an appropriate assessment of the implications of a plan or project is thus conditional on its being likely to have a significant effect on the site. Therefore, the triggering of the environmental protection mechanism provided for in Article 6(3) of the Habitats Directive does not presume - as is, moreover, clear from the guidelines for interpreting that Article drawn up by the Commission, entitled Managing Natura 2000 Sites: The provisions of Article 6 of the Habitats Directive (92/43/EEC)' - that the plan or project considered definitely has significant effects on the site concerned but follows from the mere probability that such an effect attaches to that plan or project. As regards Article 2(1) of Directive 85/337, the text of which, essentially similar to Article 6(3) of the Habitats Directive, provides that Member States shall adopt all measures necessary to ensure that, before consent is given, projects likely to have significant effects on the environment ... are made subject to an assessment with regard to their effects', the Court has held that these are projects which are likely to have significant effects on the environment. It follows that the first sentence of Article 6(3) of the Habitats Directive subordinates the requirement for an appropriate assessment of the implications of a plan or project to the condition that there be a probability or a risk that the latter will have significant effects on the site concerned. In the light, in particular, of the precautionary principle, which is one of the foundations of the high level of protection pursued by Community policy on the environment, in accordance with the first subparagraph of Article 174(2) EC, and by reference to which the Habitats Directive must be interpreted, such a risk exists if it cannot be excluded on the basis of objective information that the plan or project will have significant effects on the site concerned. Such an interpretation of the condition to which the assessment of the implications of a plan or project for a specific site is subject, which implies that in case of doubt as to the absence of significant effects such an assessment must be carried out, makes it possible to ensure effectively that plans or projects which adversely affect the integrity of the site concerned are not authorised, and thereby contributes to achieving, in accordance with the third recital in the preamble to the Habitats Directive and Article 2(1) thereof, its main aim, namely, ensuring biodiversity through the conservation of natural habitats and of wild fauna and flora.

In the light of the foregoing, the answer to Question 3(a) must be that the first sentence of Article 6(3) of the Habitats Directive must be interpreted as meaning that any plan or project not directly connected with or necessary to the management of the site is to be subject to an appropriate assessment of its implications for the site in view of the site's conservation objectives if it cannot be excluded, on the basis of objective information, that it will have a significant effect on that site, either individually or in combination with other plans or projects.

Question 3(b)

As is clear from the first sentence of Article 6(3) of the Habitats Directive in conjunction with the 10th recital in its preamble, the significant nature of the effect on a site of a plan or project not directly connected with or necessary to the management of the site is linked to the site's conservation objectives. So, where such a plan or project has an effect on that site but is not likely to undermine its conservation objectives, it cannot be considered likely to have a significant effect on the site concerned. Conversely, where such a plan or project is likely to undermine the conservation objectives of the site concerned, it must necessarily be considered likely to have a significant effect on the site. As the Commission in essence maintains, in assessing the potential effects of a plan or project, their significance must be established in the light, inter alia, of the characteristics and specific environmental conditions of the site concerned by that plan or project.

The answer to Question 3(b) must therefore be that, pursuant to the first sentence of Article 6(3) of the Habitats Directive, where a plan or project not directly connected with or necessary to the management of a site is likelyPage 99 to undermine the site's conservation objectives, it must be considered likely to have a significant effect on that site. The assessment of that risk must be made in the light inter alia of the characteristics and specific environmental conditions of the site concerned by such a plan or project.

Fourth question

By Questions 4(a) to 4(c), the national court in essence asks the Court to clarify the concepts of appropriate steps' within the meaning of Article 6(2) of the Habitats Directive and appropriate assessment' within the meaning of Article 6(3) thereof and the conditions under which an activity such as mechanical cockle fishing may be authorised.

In the light of the context of the main action, as well as the foregoing observations, and in particular the answers to the first two questions, there is no need, as stated in point 116 of the Advocate General's Opinion, to answer the fourth question as regards Article 6(2) of the Habitats Directive. As regards the concept of appropriate assessment' within the meaning of Article 6(3) of the Habitats Directive, it must be pointed out that the provision does not define any particular method for carrying out such an assessment. None the less, according to the wording of that provision, an appropriate assessment of the implications for the site concerned of the plan or project must precede its approval and take into account the cumulative effects which result from the combination of that plan or project with other plans or projects in view of the site's conservation objectives. Such an assessment therefore implies that all the aspects of the plan or project which can, either individually or in combination with other plans or projects, affect those objectives must be identified in the light of the best scientific knowledge in the field. Those objectives may, as is clear from Articles 3 and 4 of the Habitats Directive, in particular Article 4(4), be established on the basis, inter alia, of the importance of the sites for the maintenance or restoration at a favourable conservation status of a natural habitat type in Annex I to that Directive or a species in Annex II thereto and for the coherence of Natura 2000, and of the threats of degradation or destruction to which they are exposed. As regards the conditions under which an activity such as mechanical cockle fishing may be authorised, given Article 6(3) of the Habitats Directive and the answer to the first question, it lies with the competent national authorities, in the light of the conclusions of the assessment of the implications of a plan or project for the site concerned, to approve the plan or project only after having made sure that it will not adversely affect the integrity of that site. It is therefore apparent that the plan or project in question may be granted authorisation only on the condition that the competent national authorities are convinced that it will not adversely affect the integrity of the site concerned. So, where doubt remains as to the absence of adverse effects on the integrity of the site linked to the plan or project being considered, the competent authority will have to refuse authorisation. In this respect, it is clear that the authorisation criterion laid down in the second sentence of Article 6(3) of the Habitats Directive integrates the precautionary principle and makes it possible effectively to prevent adverse effects on the integrity of protected sites as the result of the plans or projects being considered. A less stringent authorisation criterion than that in question could not as effectively ensure the fulfilment of the objective of site protection intended under that provision. Therefore, pursuant to Article 6(3) of the Habitats Directive, the competent national authorities, taking account of the conclusions of the appropriate assessment of the implications of mechanical cockle fishing for the site concerned, in the light of the site's conservation objectives, are to authorise such activity only if they have made certain that it will not adversely affect the integrity of that site. That is the case where no reasonable scientific doubt remains as to the absence of such effects. Otherwise, mechanical cockle fishing could, where appropriate, be authorised under Article 6(4) of the Habitats Directive, provided that the conditions set out therein are satisfied.

In view of the foregoing, the answer to the fourth question must be that, under Article 6(3) of the Habitats Directive, an appropriate assessment of the implications for the site concerned of the plan or project implies that, prior to its approval, all the aspects of the plan or project which can, by themselves or in combination with other plans or projects, affect the site's conservation objectives must be identified in the light of the best scientific knowledge in the field. The competent national authorities, taking account of the appropriate assessment of the implications of mechanical cockle fishing for the site concerned in the light of the site's conservation objectives, are to authorise such an activity only if they have made certain that it will not adversely affect the integrity of that site. That is the case where no reasonable scientific doubt remains as to the absence of such effects.

Fifth question

In the light of the finding in paragraph 51 above, it is not necessary to consider the fifth question in so far as it relates to Article 6(2) of the Habitats Directive. It is therefore appropriate to consider that question only in so far as it concerns Article 6(3) of the Habitats Directive.

Page 100

By its fifth question, the national court asks in essence whether, when a national court is called on to ascertain the lawfulness of an authorisation for a plan or project within the meaning of Article 6(3) of the Habitats Directive, it may examine whether the limits of discretion of the competent national authorities laid down by that provision have been complied with even though it has not been transposed into the legal order of the Member State concerned despite the expiry of the time-limit laid down for that purpose.

It should be recalled that the obligation of a Member State to take all the measures necessary to achieve the result prescribed by a directive is a binding obligation imposed by the third paragraph of Article 249 EC and by the Directive itself. That duty to take all appropriate measures, whether general or particular, is binding on all the authorities of Member States including, for matters within their jurisdiction, the courts. As regards the right of an individual to rely on a directive and of the national court to take it into consideration, it would be incompatible with the binding effect attributed to a directive by Article 249 EC to exclude, in principle, the possibility that the obligation which it imposes may be relied on by those concerned. In particular, where the Community authorities have, by Directive, imposed on Member States the obligation to pursue a particular course of conduct, the effectiveness of such an act would be weakened if individuals were prevented from relying on it before their national courts, and if the latter were prevented from taking it into consideration as an element of Community law in order to rule whether the national legislature, in exercising the choice open to it as to the form and methods for implementation, has kept within the limits of its discretion set by the Directive. That also applies to ascertaining whether, failing transposition into national law of the relevant provision of the Directive concerned, the national authority which has adopted the contested measure has kept within the limits of its discretion set by that provision. More particularly, as regards the limits of discretion set by Article 6(3) of the Habitats Directive, it follows from that provision that in a case such as that in the main action, the competent national authorities, taking account of the conclusions of the appropriate assessment of the implications of mechanical cockle fishing for the site concerned in the light of the site's conservation objectives, are to authorise such an activity only if they have made certain that it will not adversely affect the integrity of that site, that being the case if there remains no reasonable scientific doubt as to the absence of such effects. Such a condition would therefore not be observed were the national authorities to authorise that activity in the face of uncertainty as to the absence of adverse effects for the site concerned. It follows that Article 6(3) of the Habitats Directive may be taken into account by the national court in determining whether a national authority which has granted an authorisation relating to a plan or project has kept within the limits of the discretion set by the provision in question.

Consequently, the answer to the fifth question must be that where a national court is called on to ascertain the lawfulness of an authorisation for a plan or project within the meaning of Article 6(3) of the Habitats Directive, it can determine whether the limits on the discretion of the competent national authorities set by that provision have been complied with, even though it has not been transposed into the legal order of the Member State concerned despite the expiry of the time-limit laid down for that purpose.