Order of the President of the of the General Court of 7 November 2019 - AMVAC Netherlands v Commission

(Case T-317/19 R)

(Application for interim measures - Plant protection products - Regulation (EC) No 1107/2009 - Active substance ethoprophos - Conditions for approval for placing the substance on the market - Application for suspension of operation - Lack of urgency)

  1. Interim relief - Suspension of operation of a measure - Interim measures - Conditions for granting - Prima facie case - Urgency - Serious and irreparable damage - Cumulative nature - Balancing of all the interests involved - Order of examination and method of verification - Discretion of the court hearing the application for interim relief

    (Arts 256(1), 278 and 279 TFEU; Rules of Procedure of the General Court, Art. 156(4))

    (see paras 14-17)

  2. Interim relief - Suspension of operation of a measure - Interim measures - Conditions for granting - Urgency - Serious and irreparable damage - Burden of proof borne by the party seeking the interim measure

    (Arts 278 and 279 TFEU; Rules of Procedure of the General Court, Art. 156(4))

    (see para. 20)

  3. Interim relief - Suspension of operation of a measure - Interim measures - Conditions for granting - Urgency - Serious and irreparable damage - Burden of proof - Obligation to provide concrete and precise indications, supported by detailed documentary evidence

    (Arts 278 and 279 TFEU; Rules of Procedure of the General Court, Art. 156(4))

    (see paras 21-23, 37)

  4. Interim relief - Suspension of operation of a measure - Interim measures - Conditions for granting - Serious and irreparable damage - Financial loss - Serious nature of the harm - Situation liable to endanger the existence of the applicant company - Assessment in the light of the size and turnover of the undertaking and the situation of the group to which it belongs - Examination of the circumstances of each case

    (Arts 278 and 279 TFEU)

    (see paras 27-30, 33, 36)

  5. Interim relief - Suspension of operation of a measure - Conditions for granting - Urgency - Serious and irreparable damage - Financial loss - Irreparable alteration in market shares - Included - Conditions - Burden of proof - No substitute product in the portfolio of substances - Irrelevant

    (Arts 278 and 279 TFEU)

    (see paras 43, 44, 46, 47, 52)

  6. Interim relief - Suspension of operation of a measure - Interim measures - Conditions for granting - Urgency - Serious and irreparable...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT