UK Coal plc v Commission of the European Communities.
| Jurisdiction | European Union |
| Court | General Court (European Union) |
| ECLI | ECLI:EU:T:2001:188 |
| Docket Number | T-63/99,T-12/99 |
| Date | 12 July 2001 |
| Procedure Type | Recurso de anulación - infundado |
Judgment of the Court of First Instance (Second Chamber, extended composition) of 12 July 2001. - UK Coal plc v Commission of the European Communities. - ECSC Treaty - Decision No 3632/93/ECSC - Operating aid and aid for the reduction of activity - Authorisation ex post facto of aid already paid - Improvement of the viability of recipient undertakings - Degression of aid - Bonus paid to underground mineworkers (Bergmannsprämie) - Amendment of a modernisation, rationalisation and restructuring plan - Taking account of a concentration between undertakings - Statement of reasons. - Joined cases T-12/99 and T-63/99.
European Court reports 2001 Page II-02153
Summary
Parties
Grounds
Decision on costs
Operative part
1. Actions for annulment - Action brought by an undertaking against an individual ECSC decision not addressed to it - Decision authorising the grant of aid to a competitor - Undertakings in competition - Concept - Criteria
(ECSC Treaty, Arts 4(c) and 33, second para.; General Decision No 3632/93)
2. ECSC - Aid to the coal industry - Authorisation by the Commission - Authorisation after payment of the aid - Whether permissible
(ECSC Treaty, Art. 4(c); General Decision No 3632/93, Art. 9(5))
3. ECSC - Aid to the coal industry - Prohibition - Authorisation by the Commission - Conditions - Improvement in economic viability
(ECSC Treaty, Art. 4(c); General Decision No 3632/93, Arts 2(1) and 3)
4. ECSC - Aid to the coal industry - Prohibition - Authorisation by the Commission - Conditions - Degression of aid
(ECSC Treaty, Art. 4(c); General Decision No 3632/93, Arts 2(1) and 3(1) and (2))
5. Actions for annulment - Action brought under the first paragraph of Article 33 of the ECSC Treaty - Pleas in law - Manifest failure by the Commission to observe the provisions of the Treaty or any rule of law relating to its application - Meaning - Limits on the Court's power of assessment
(ECSC Treaty, Art. 33, first para.)
6. ECSC - Aid to the coal industry - Operating aid and aid for the reduction of activity - Prohibition - Authorisation by the Commission - Conditions - Covering of the difference between production costs and the selling price on the world market - Scrutiny by the Commission in advance and after the event - Scope of the scrutiny
(ECSC Treaty, Arts 4(c), 35 and 88; General Decision No 3632/93, Arts 3(1) and 9(1), (2), (4) and (6))
7. Acts of the institutions - Statement of reasons - Obligation - Scope - ECSC Decision
(ECSC Treaty, Arts 15, first para., and 33, second para.)
Summary
1. In deciding when an undertaking is concerned because it is in competition with another undertaking, it should be noted, first, that the conditions governing admissibility laid down by the second paragraph of Article 33 of the ECSC Treaty are less strict than those for an action for annulment brought under the second paragraph of Article 173 of the EC Treaty (now, after amendment, the second paragraph of Article 230 EC). Also, the provisions of the ECSC Treaty concerning the right of individuals to bring an action must be interpreted widely in order to safeguard their legal protection.
Second, with regard specifically to the State aid rules in the ECSC Treaty, Article 4(c) of the Treaty lays down such a general, strict and unconditional prohibition on aid that it is unnecessary to examine whether, in point of fact, there is interference or potential interference with the conditions of competition in order to be able to declare aid incompatible with the common market. That prohibition does not presuppose that the aid is such as to distort or threaten to distort competition by favouring certain undertakings or the production of certain goods.
Moreover, Article 4(c) of the ECSC Treaty does not contain a de minimis rule under which aid entailing only a slight distortion of competition would escape from the prohibition laid down. Nor does Decision No 3632/93 establishing Community rules for State aid to the coal industry contain a de minimis rule, such as that laid down for the regime governing State aid falling within the EC Treaty.
It follows that the admissibility of an action brought under the second paragraph of Article 33 of the ECSC Treaty by a Community coalmining undertaking, complaining of an infringement of Article 4(c) of that Treaty and directed against a decision by the Commission authorising the grant of State aid to another Community coalmining undertaking, cannot depend on actual or potential competition being proved. Having regard to the specific features of the ECSC regime which are mentioned above, it is sufficient to establish that there is a body of evidence supporting the conclusion that competition between the undertakings in question is not an unrealistic possibility.
( see paras 53-56 )
2. No provision of Decision No 3632/93 establishing Community rules for State aid to the coal industry prohibits the Commission from examining the compatibility of planned aid with the common market solely because the Member State which notified that aid has already paid it without waiting for prior authorisation. On the contrary, in so far as Article 9(5) of that decision makes the repayment of aid paid in anticipation expressly subject to the condition that the Commission must have refused authorisation, it necessarily implies that the Commission has the power to grant authorisation in such a situation. Finally, at a more general level, the substantive and procedural provisions in that decision and the system established by Articles 92 and 93 of the EC Treaty (now, after amendment, Articles 87 and 88 EC) do not differ on points of principle, so that it would not be justified to interpret the provisions of the decision, in relation to Article 4(c) of the ECSC Treaty, more restrictively than paragraphs 2 and 3 of Article 92 of the EC Treaty in relation to paragraph 1 thereof, and the Commission is obliged, under Article 92 of the EC Treaty, to make an ex post facto assessment of aid already paid.
( see para. 68 )
3. No provision of Decision No 3632/93 establishing Community rules for State aid to the coal industry states expressly that operating aid must be strictly reserved for undertakings with reasonable chances of achieving economic viability in the long term, in the sense that they must be capable of meeting competition on the world market on their own merits. The relevant provisions of the decision do not require that the undertaking in receipt of operating aid achieve viability by the end of a fixed period. They require only that economic viability improve, the reason for that open-ended formulation being the structural uncompetitiveness faced by the Community coal industry because most of its undertakings remain uncompetitive in relation to imports from non-member countries. It follows that improvement in the economic viability of a given undertaking necessarily means no more than a reduction in the level of its non-profitability and its non-competitiveness.
( see para. 81 )
4. As provided in Article 3(1) of Decision No 3632/93 establishing Community rules for State aid to the coal industry, operating aid is intended solely to cover the difference between production costs and the selling price on the world market. By virtue of Article 3(2) of the decision, that aid may be authorised only if there is at least a trend towards a reduction in the production costs of the undertakings receiving it. In that context, the first indent of Article 2(1) of the decision sets as one of the objectives to be attained that of achieving degression of aids, an aim to be achieved in the light of coal prices on international markets. In this connection, the economic realities - namely the structural unprofitability of the Community coal industry - in the light of which the decision was adopted must be taken into account when interpreting Article 2(1) of the decision.
As the Community institutions, the Member States and the undertakings concerned do not have a significant influence on the world market price, the Commission cannot be reproached for having attached overriding importance, in terms of a degression of aid to the coal industry, to reducing production costs, since any reduction necessarily means that the volume of aid is smaller than if the reduction had not occurred, irrespective of movements in world market prices.
( see paras 117, 119-121 )
5. Where the Court conducts a review under the first and second paragraphs of Article 33 of the ECSC Treaty, it must, as regards the assessment of complex economic facts or circumstances carried out by the Commission which supports a decision contested before it, confine itself to ascertaining whether the institution which took that decision manifestly failed to observe the provisions of the ECSC Treaty or any rule of law relating to its application, the term manifestly in Article 33 presupposing a breach of the legal provisions so serious that it appears to derive from a manifest error in the assessment, having regard to the provisions of the ECSC Treaty, of the situation in respect of which the decision was taken.
( see para. 159 )
6. By virtue of Article 3(1) of Decision No 3632/93 establishing Community rules for State aid to the coal industry, operating aid and aid for the reduction of activity are intended to cover the difference between production costs and the selling price freely agreed between the contracting parties in the light of the conditions prevailing on the world market. It follows that any matter of a financial nature which - by reducing costs or increasing revenue - causes the aid notified to exceed that difference, results in the corresponding fraction of aid being no longer covered by that basic rule and therefore incapable of authorisation, as operating aid or aid for the reduction of activity, under that decision. Accordingly, such aid not covered...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Start Your 7-day Trial
-
UK Coal plc v Commission of the European Communities.
...relating to it. Those actions were registered in the Court under case numbers T-12/99 and T-63/99. By judgment of 12 July 2001 in Joined Cases T-12/99 and T-63/99 UK Coal v Commission [2001] ECR II-0000, the Court of First Instance dismissed them as unfounded.4 By application lodged on 3 Ma......